AC Replacement Project
Project Name: AC Replacement Project South
Project Date: August 2007 to July 2010
Project Description:
The project aims to replace 2800km of asbestos cement pipes with modified polyvinyl chloride (mPVC) pipe, thereby ensuring the reliability of water supply. The project is expected to reduce water loss by an estimated 10.6%.
The old AC pipes will be replaced with in most areas. However in the CBD High Density Polyethylene Pipes (HDPE) pipes are being used, because this type of material is more suited to the trenchless technology methods being used.
Project Details:
Replacement of the secondary AC (undipped 150mm diameter and smaller pipelines with uPVC pipe lines and the replacement of the domestic connections from the saddle on the new main to the foot of the riser of the house hold meters in HDPE pipework
Project Value: R 500 Million
Client:
Ethekwini Water and Sanitation
Consultants
CBI Consulting Engineers (Pty) Ltd